Cuckoo Hill Solar Farm

Welcome to our consultation website

Powering over 10,000 homes with clean, renewable energy, while supporting nature and providing lasting benefits for the local community.

Qualitas Energy is working with the Ernest Cook Trust to bring forward plans for Cuckoo Hill Solar Farm on land at East Farm, Burton Lazars, Melton Mowbray, LE14 2UW.

The proposed 40MW Cuckoo Hill Solar Farm reflects a combination of Qualitas Energy’s energy expertise with the Ernest Cook Trust’s responsible progressive land management, creating a development that advances clean energy, community engagement, and long-term care for the countryside.

Site Location

Cuckoo Hill Solar Farm is being proposed on land at East Farm, Burton Lazars, Melton Mowbray, LE14 2UW. The Site is located approximately 1.6 km east of the village of Burton Lazars and approximately 2.8 km to the west of Melton Mowbray.

The total Site Area is c.98 hectares (ha), this includes the main development area and cable route. The main development area where panels will be located is 88 ha.

Environmental Impact Assessment (EIA) Scoping Request

We recently submitted an Environmental Impact Assessment (EIA) Scoping Request to Melton Borough Council. This marks an early step in the planning process, focused on identifying the environmental information about the site, and determining the environmental topics that will need to be assessed in detail. This process will help the design team understand potential impacts, identify measures to mitigate any adverse effects, and maximise opportunities for positive outcomes.

It is our intention that the planning application will incorporate measures both to mitigate potential adverse environmental effects and to enhance environmental benefits, wherever possible, through thoughtful design.

An Environmental Statement (ES) will also be prepared as part of this application. This will outline the reasonable alternatives considered, describe the baseline environment, assess likely significant effects, and set out the measures proposed.

Indicative Site Layout and Opportunities Plan

Qualitas Energy

The Ernest Cook Trust


EIA Scoping Submitted to Melton Borough Council

w/c 13th October 2025


October - December 2025

Consultation Period


November 2025

Consultation Event


Early 2026

Finalise Project Design


September 2026

Planning Application Submission